Public Inquiry for the Planning Appeal at Land at M40 J10, Baynards Green, Oxfordshire

Appeal Core Documents B - Information Submitted as part of the Application

 

The following documents are available to view in the Appeal Core Documents B download

B – Appeal B: Information Submitted as part of the Application

 

Documents which the Application was Determined on

B1

Application Form

B2

Plans on which LPA’s decision was based

B2.1

20005-TP-007 Site Location Plan Eastern Parcel

B2.2

20005-TP-025 Illustrative Typical Elevations

B2.3

20005-TP-011 Existing Site Levels - Eastern Parcel

B2.4

20005-TP-008C Parameter Plan 06 Land Use

B2.5

20005-TP-009C Parameter Plan 07 Building Heights

B2.6

20005-TP-010A Parameter Plan 08 Vegetation Retention and Removal

B2.7

20005-TP-020A Illustrative Masterplan

B2.8

20005-TP-026 Site Sections Eastern Parcel A43

B2.9

14047_P03D Landscape Strategy Plan

B2.10

14047_P16A Landscape Parameter Plan

B2.11

17213-35-GA D Eastern Access General Arrangement with B4100 Bus Stops & Crossing

B3

Cover Letter (dated 21 September 2021)

B4

Cover Letter – Application Update (31 May 2024)

B5

Response to Consultation Comments (April 2025)

B6

Cover Letter Updated Documents (23 April 2025)

B7

Appeal Warning Letter (May 2025)

B8

Planning Statement (September 2021)

B9

Planning Application Update (April 2025)

B10

Planning Statement Addendum (November 2025)

B11

Draft NPPF Note (December 2025)

B12

Development Specification

B13

Environmental Statement (September 2024):

B13.1

ES Volume I Chapter 1 Introduction

B13.2

ES Volume I Chapter 2 Site and Setting

B13.3

ES Volume I Chapter 3 EIA Methodology

B13.4

ES Volume I Chapter 4 Alternatives

B13.5

ES Volume I Chapter 5 Description of the Development

B13.6

ES Volume I Chapter 6 Construction

B13.7

ES Volume I Chapter 7 Socio-Economics

B13.8

ES Volume I Chapter 8 Transport & Access

B13.9

ES Volume I Chapter 9 Air Quality

B13.10

ES Volume I Chapter 10 Noise & Vibration

B13.11

ES Volume I Chapter 11 Cultural Heritage

B13.12

ES Volume I Chapter 12 Biodiversity

B13.13

ES Volume I Chapter 13 Landscape and Visual Impacts

B13.14

ES Volume I Chapter 14 Climate Change & Greenhouse Gases

B13.15

ES Volume I Chapter 15 - Hydrology, Flood Risk and Drainage

B13.16

ES Volume I Chapter 16 Effect Interactions

B13.17

ES Volume I Chapter 17 Summary of Mitigation, Monitoring and Residuals

B13.18

ES Non-Technical Summary

B14

B14: ES (2024) Appendices

B14.1

ES (2024) Appendix 3.1: Location of Specified Information in the ES

B14.2

ES (2024)  Appendix 3.2: EIA Scoping Report (June 2021)

B14.3

ES (2024) Appendix 3.3: CDC EIA Scoping Opinion (July 2021) and scoping consultation responses

B14.4

ES (2024) Appendix 3.4: a) Enabling Works EIA Screening Request b) CDC Screening Opinion (August 2021)

B14.5

ES (2024) Appendix 3.5: List of Cumulative Schemes

B14.6

ES (2024) Appendix 5.1: Parameter Plans and Detailed Drawings

B14.7

ES (2024) Appendix 5.2: Development Specification

B14.8

ES (2024)  Appendix 6.1: Framework CEMP – East

B14.9

ES (2024) Appendix 6.2: Framework CEMP – West

B14.10

ES (2024) Appendix 8.1: Transport Assessment

B14.11

ES (2024) Appendix 8.1a: Transport Assessment Addendum

B14.12

ES (2024) Appendix 8.2: Framework Travel Plan (Western Site)

B14.13

ES (2024) Appendix 8.2: Framework Travel Plans (Eastern Site)

B14.14

ES (2024) Appendix 9.1: Legislation and Policy Context

B14.15

ES (2024) Appendix 9.2: Construction Dust Assessment Methodology

B14.16

ES (2024) Appendix 9.3: Environmental Protection UK (EPUK) / Institute of Air Quality Management (IAQM) Planning for Air Quality Guidance

B14.17

ES (2024) Appendix 9.4: Modelling Methodology

B14.18

ES (2024) Appendix 9.5: Construction Mitigation Measures

B14.19

ES (2024) Appendix 9.6: Cumulative Modelling Results

B14.20

ES (2024) Appendix 9.7: Glossary and Appendices References

B14.21

ES (2024) Appendix 9.8: Biodiversity Air Quality Modelling Assessment

B14.22

ES (2024) Appendix 10.1: Technical Glossary

B14.23

ES (2024) Appendix 10.2: Legislation, Planning Policy and Guidance – Further Information

B14.24

ES (2024) Appendix 10.3: Construction Noise and Vibration

B14.25

ES (2024) Appendix 10.4: Operational Sound

B14.26

ES (2024) Appendix 10.5: Operational Road Traffic Noise

B14.27

ES (2024) Appendix 10.6: Road Traffic Noise Contours

B14.28

ES (2024) Appendix 11.1: Cultural Heritage Desk-Based Assessment (DBA)

B14.29

ES (2024) Appendix 11.2: Geophysical Survey - Western Site

B14.30

ES (2024) Appendix 11.3: Geophysical Survey - Eastern Site

B14.31

ES (2024) Appendix 11.4: Archaeological Evaluation Trenching

B14.32

ES (2024) Appendix 11.5: Relevant Planning Policy and Guidance

B14.33

ES (2024) Appendix 12.1: Legislation and Planning Policy

B14.34

ES (2024) Appendix 12.2: Protected Species Survey Methodology and Results

B14.35

ES (2024) Appendix 12.3a: Biodiversity Net Gain Assessment, Eastern Site

B14.36

ES (2024) Appendix 12.3b: Biodiversity Net Gain Assessment, Western Site

B14.37

ES (2024) Appendix 12.3c: Onsite Post-intervention BNG Plan

B14.38

ES (2024) Appendix 12.3d: Offsite Post-intervention BNG Plan

B14.39

ES (2024) Appendix 12.4: Habitat Features, Badger and Preliminary Bat Roost Assessment Plan [Redacted]

B14.39.1

ES (2024) Appendix 12.4: Habitat Features, Badger and Preliminary Bat Roost Assessment Plan [Unredacted – CONFIDENTIAL]

B14.40

ES (2024) Appendix 12.5: Designated sites and Ancient Woodland Plan

B14.41

ES (2024) Appendix 12.6: Bat Survey Location Plan

B14.42

ES (2024) Appendix 12.7: Bat Activity Transect Survey Results Plan

B14.43

ES (2024) Appendix 12.8: Breeding Bird Survey Results Plan

B14.44

ES (2024) Appendix 12.9: Hazel Dormouse Survey Results Plan

B14.45

ES (2024) Appendix 13.1: Figures

B14.46

ES (2024) Appendix 13.2: Updated Photoviewpoint Sheets and Methodology

B14.47

ES (2024) Appendix 13.3: LVIA Methodology

B14.48

ES (2024) Appendix 13.4: Extracts from landscape character assessments

B14.49

ES (2024) Appendix 13.5: Scoped out Photoviewpoints

B14.50

ES (2024) Appendix 13.6: Correspondence with CDC

B14.51

ES (2024) Appendix 13.7: Agreement with LUC re. scope of further assessment

B14.52

ES (2024) Appendix 13.8: Correspondence with CDC and LUC further to meeting with Tritax team

B14.53

ES (2024) Appendix 13.9: Cumulative ZTV Plan

B14.54

ES (2024) Appendix 13.10: Cumulative Photoviewpoint Sheets

B14.55

ES (2024) Appendix 13.11: Residential Visual Amenity Assessment

B14.56

ES (2024) Appendix 14.1: Climate Change

B14.57

ES (2024) Appendix 15.1: Site Specific Flood Risk Assessment (FRA) and Drainage Strategy. Issue 3 (January 2024) by Bailey Johnson Hayes

B14.58

ES (2024) Appendix 15.2: Report on Preliminary Phase II Ground Investigation at Land Adjacent to Junction 10 M40, Ardley. Issue 2 (August 2021) by Applied Geology

B14.59

Transport Topic Paper Addendum dated 3 February 2025

B14.60

Transport Topic Paper Addendum Appendix G Revision 1 Dated 13 March 2025

B15

EIA Technical Note (January 2025)

B16

ES Addendum (November 2025)

B16.1

ESA Volume I Chapter 1 Introduction

B16.2

ESA Volume I Chapter 2 Approach to ES Addendum

B16.3

ESA Volume I Chapter 3 Cumulative Effects Assessment

B16.4

ESA Volume I Chapter 4 Socio-Economics

B16.5

ESA Volume I Chapter 5 Transport and Access

B16.6

ESA Volume I Chapter 6 Biodiversity

B16.7

ESA Volume I Chapter 7 Landscape and Visual

B16.8

ESA Volume I Chapter 8 Summary

B16.9

ESA Appendix 1.1 CDC Regulation 25 Letter (dated 30 October 2025)

B16.10

ESA Appendix 3.1 Updated List of Cumulative Schemes

B16.11

ESA Appendix 5.1 Transport Sensitivity Testing Technical Note

B16.12

ESA Appendix 6.1 CDC Consultation Emails

B16.13

ESA Appendix 6.2 Updated Ecological Survey Results (badger, dormouse, breeding birds, etc.)

B16.14

ESA Appendix 6.3 Draft Habitat Management and Maintenance Plan

B16.15

ESA Appendix 6.4 Updated Landscape Strategy Plan

B16.16

ESA Appendix 6.5 Updated Biodiversity Net Gain (BNG) Metrics (East and West Development)

B16.17

ESA Non-Technical Summary

B17

Economic Assessment (May 2024)

B18

P0188-01 Lighting Assessment (September 2021)

B19

ESC1717 Final Sustainability Statement 

B20

C792 Issue 2 Agricultural Land Classification

B21

Design and Access Statement

B22

Logistics Market and Land Availability Report (September 2021)

B23

Logistics Market and Land Availability Report Update (May 2024)

B24

Supplementary Report to Logistics Market Assessment and Land Availability Report (January 2025)

B25

Cherwell Site Analysis (January 2025)

B26

14047_R01a_JP_MM Preliminary Arboricultural Impact Assessment

B27

Transport Topic Paper May 2024

B28

NOT USED

B29

ES Sensitivity Testing Revision 2

B30

BJH-AXISJ10-FRA-V4 Issue 4 Flood Risk Assessment (update to Appendix 15.1 of ES)

B31

 16293/R010/GS/TC/DM Ecology Rebuttal (04 November 2024) - CONFIDENTIAL

B32

14047_R11b_MJ Outline Off-Site Habitat Management and Maintenance Plan

B33

14047_R12_MJ Outline On-Site Habitat Management and Maintenance Plan

B34

BJH-ARDLEY Axis J10, Technical Note Issue 2

B35

Superseded Documents Referenced in Evidence

B35.1

Environmental Statement (September 2021):

ES Volume I: Chapter 8 Transport and Access

B35.2

NOT USED

B35.3

ES (2021) Appendix 8.2: Framework Travel Plan (Western Site)

B35.4

ES (2021) Appendix 8.2: Framework Travel Plan (Eastern Site)

B35.5

Consultation Response – Technical Note dated 1 November 2022

B36

EIA Scoping Report dated 22 June 2021

B37

Scoping Letter Response from CDC dated 29 July 2021

B38

Relevant Correspondence (Landscape) Tyler Grange to CDC / LUC 22.04.22

B39

Environmental Statement (September 2021):

ES Volume I: Chapter 12 Ecology and Biodiversity

 

Other Relevant Documents

B40

ES (2021) Appendix 8.1: Transport Assessment

B41

Consultation Response – Technical Note dated 1 November 2022

B42

DTA letter to CDC dated 10 February 2025